[Parks and Recreation on January 13, 2025.]

[00:00:10]

WHY DID YOU WAIT SO LONG TO TELL ME THAT? COMMENTS ON NON-AGENDA ITEMS. THERE IS NO ONE IN THE GALLERY, SO I'M GOING TO ASSUME WE HAVE NO MEMBERS OF THE PUBLIC TO SPEAK. IS THAT TRUE? ALL RIGHT. OKAY. WELL, WE'LL JUMP RIGHT INTO REGULAR AGENDA ITEMS. THE FIRST BEING CONSIDER AND ACT UPON THE APPROVAL OF THE NOVEMBER 6TH, 2024, PARKS AND RECREATION BOARD REGULAR MEETING MINUTES. I INVITE BOARD MEMBERS TO SHARE ANY QUESTIONS OR COMMENTS. THE BOARD MINUTES ARE INCLUDED IN YOUR PACKET. IF THERE ARE NO QUESTIONS OR COMMENTS, I'D BE OPEN TO A MOTION ON APPROVING THE MINUTES FROM NOVEMBER 6TH, 2024. YES. NICHOLAS PUENTE. I WOULD LIKE TO MAKE A MOTION TO APPROVE THE ITEM AS PRESENTED. THANK YOU SIR. DO WE HAVE A SECOND TO THE MOTION? SCOTT HAVEL. I'LL SECOND. THANK YOU SIR. WE WILL BE VOTING BY HAND TONIGHT. SO WHEN YOU ARE READY, ALL EYES RAISE HAND. ONE, TWO, THREE. FOUR AND FIVE. UNANIMOUSLY. OH, UNANIMOUSLY. THE MOTION CARRIES. WITH AGAIN CINDY TURNER AND GLORIA SUAREZ ABSENT FROM THE MEETING. ALL RIGHT. MOVING RIGHT ALONG INTO A WORK SESSION. WE'VE GOT SOME PROJECT UPDATES. MR. STOWERS, COULD YOU TAKE US THROUGH THAT? ALRIGHTY. SO WE'VE GOT A FEW OF THEM. WE'LL START WITH PICKLEBALL EXPANSION. AGAIN, THIS IS OVER AT COMMUNITY PARK. WE'RE DOUBLING THE SIZE OF THAT PICKLEBALL COURT. SO RIGHT NOW IT'S THREE COURTS. WE'RE MOVING TO SIX COURTS NOW.

CONSTRUCTION HAS ACTUALLY STARTED TODAY. RIGHT NOW THEY'RE JUST WORKING ON FORMING WHERE THE CONCRETE IS GOING TO GO. THEY'RE GOING TO WORK WITH ANOTHER CONTRACTOR ON INSTALLING THE POST AND WHATNOT. BUT ONCE THAT ONCE THE CONCRETE IS POURED, WE'VE GOT 28 DAYS. WE GOT TO WAIT FOR IT TO CURE. AND THEN WE'LL BRING THE SURFACING COMPANY IN. THEY'LL SURFACE THE NEW COURT. AT THAT POINT, THE COURT WILL BE ALL SIX COURTS WILL BE ALLOWED TO BE USED.

HOWEVER, IN THE MEANTIME, WE'RE ALSO GOING TO BE LOOKING TO SHADE THE ENTIRE SIX COURTS AND INSTALL LIGHTING UNDERNEATH THE SHADE SO THAT THE COURTS CAN BE USED IN THE EVENING HOURS AND WHATNOT. SO THAT PROJECT HAS STARTED. I IMAGINE IT'LL THE COURTS THEMSELVES SHOULD BE DONE EARLY 2025. AS FAR AS THE SHADE AND THE LIGHTING, WE'RE STILL WORKING THROUGH SOME, YOU KNOW, NUMBERS THERE AND TRYING TO GET THE RIGHT SHADE AND THE LIGHTS AND EVERYTHING INSTALLED. SO THAT WILL KIND OF COME ON AFTERWARDS. BUT IT SHOULDN'T IMPACT BEING ABLE TO OPEN THE COURTS OR NOT. ANY QUESTIONS ON PICKLEBALL? SCOTT, JUST SUPER QUICK QUESTION. DOES WILL, WHEN YOU SAID THAT YOU'RE DOING THE SURFACING, WILL THAT TAKE DOWN THE THREE THAT ARE IN PLAY OR THAT HAVE NO EFFECT ON THE THREE? SO WHEN WE START DOING THE FENCE WORK, WE WILL HAVE TO SHUT DOWN THE THREE EXISTING COURTS. MAINLY BECAUSE WE'VE GOT TO ADD GATES TO THE BACK SO THAT YOU CAN GET THROUGH ALL OF THEM, SO THAT THERE WILL BE A TIME THAT THE THREE EXISTING COURTS WILL BE SHUT DOWN. IT SHOULDN'T BE A LONG PROCESS THOUGH. DOES THAT HELP? ANSWER? AWESOME.

ALRIGHTY, MOVING ON TO FOUNDERS PARK. SO IF YOU REMEMBER LAST BUDGET LAST YEAR WE RENOVATED THE NORTH WEST FIELDS AT FOUNDERS PARK. I BELIEVE IT WAS THREE. IT WAS FIELDS ONE, ONE, TWO AND THREE. WE ARE NOW MOVING FORWARD. COUNCIL JUST APPROVED US TO GO AHEAD AND RENOVATE FIELDS FOUR AND FIVE, WHICH ARE WHAT WE'RE CALLING THE SOUTH PORTION. THEY SHOULD BE GETTING STARTED ON THAT HERE IN THE NEXT COUPLE OF WEEKS. WE'RE SAYING FEBRUARY, THEY'LL START TAKING OFF THE TURF ON THOSE FIELDS AND THEN THEY'LL START REWORKING THEM. THEY'LL RE IRRIGATE THEM.

AND THEN SAND THEM, WHICH IS JUST PUTTING A COUPLE INCHES OF SAND ON TOP OF THEM TO HELP WITH DRAINAGE AND THEN RE SORTING THEM. WE EXPECT THOSE FIELDS TO BE OUT PRETTY MUCH ALL SPRING.

[00:05:03]

AND THEN WE'LL START ALLOWING PEOPLE TO OR YOUTH ASSOCIATIONS TO PLAY ON THEM AGAIN IN THE FALL. SO THESE ARE PREDOMINANTLY FOOTBALL. FOOTBALL USES FIELDS FOUR AND FIVE. BUT I KNOW SOCCER USES THEM AS WELL. SO IT'LL BE YOU KNOW FIELDS WILL BE DOWN FOR A LITTLE BIT AT LEAST FOR THE SPRING. BUT AT LEAST THE FALL SEASON WILL END UP HAVING THAT WHOLE SIDE NOW FULLY RENOVATED.

SO IT SHOULD BE GOOD. ANY QUESTIONS ON THAT RENOVATION? THAT ONE ALSO DID COME IN A LITTLE CHEAPER THAN WHAT WE BUDGETED FOR. I WANTED TO ADD THAT MAINLY BECAUSE WITH THE FIRST RENOVATION, WE DID SO MUCH UPFRONT WORK. ELECTRICAL, WATER SUPPLY, IRRIGATION PUMP, ALL OF THAT STUFF WENT WITH THE FIRST RENOVATION. NOW THIS ONE. ALL THEY LITERALLY HAVE TO DO IS JUST TIE INTO THAT, AND THEN THEY DON'T HAVE TO WAIT ON POWER. THEY DON'T HAVE TO WAIT ON SOME OF THE OTHER THINGS THAT KIND OF DELAYED THEM A LITTLE BIT. SO THIS ONE SHOULD GO A LOT FASTER, A LOT SMOOTHER. AND IT CAME IN SIGNIFICANTLY CHEAPER. YES, SCOTT IT IS. YOU KNOW, I DID WANT TO JUST JUMP THE LINE. WHEN YOU'RE WORKING ON THOSE, WILL IT TAKE DOWN ONE, TWO AND THREE. LIKE WILL YOU BE BLOCKING THOSE FIELDS OFF WHILE WE'RE DOING THE WORK OR WILL THEY KIND OF GO AS NORMAL? IT SHOULDN'T IMPACT FIELDS ONE THROUGH THREE AT ALL. NOW WE ARE MEETING BECAUSE THIS IS OBVIOUSLY TAKING A FOOTBALL OUT FOR THE SPRING SEASON. AND I KNOW THAT THEY DO RUN A SPRING LEAGUE. SO THERE IS GOING TO BE AND WE'RE ACTUALLY GOING TO BE MEETING TOWARDS THE END OF THIS MONTH. EXCUSE ME, BUT THERE MIGHT BE SOME IMPACT TO SOCCER BECAUSE THEY ARE GOING WE'RE GOING TO HAVE TO TRY TO MOVE FOOTBALL SOMEWHERE FOR THE SPRING, BUT WE DO PLAN ON TRYING TO WORK THAT OUT AT THE END OF THIS MONTH. SO THERE'LL BE SOME IMPACT, BUT NOT CLOSURES. ALL RIGHT. SO MOVING OVER TO THE BROWN HOUSE. SO LAST YEAR WE ACTUALLY HAD FUNDS TO LOOK AT REDOING THE EXTERIOR A LITTLE BIT. JUST KIND OF FOR A LACK OF A BETTER TERM, KIND OF GIVING IT A LITTLE BIT OF A FACELIFT. YOU KNOW, THERE'S SOME ROTTING WOOD. IT NEEDS A PAINT JOB. SO WE HAD FUNDS IN THE BUDGET TO DO THAT LAST YEAR. HOWEVER, WE WEREN'T ABLE TO WE KNEW THAT THE FACILITY WAS BASICALLY GOING TO BE DOWN FOR A FEW MONTHS FOR THAT TO HAPPEN. WE DIDN'T WANT TO IMPACT A LOT OF THE HOLIDAY EVENTS THAT WE HAD COMING UP. SO WE CARRIED THAT MONEY OVER INTO THIS BUDGET YEAR. INCREASED IT A LITTLE BIT. AND SO NOW WE'RE GOING TO BE STARTING THAT PROJECT TO ACTUALLY SHOULD BE GETTING STARTED NEXT WEEK. BUT WHAT YOU'RE GOING TO SEE THERE IS COLORS AREN'T GOING TO CHANGE. THEY'RE GOING TO KEEP THE EXACT SAME COLORS. IT'S JUST THERE ARE A LOT OF WOOD. I KNOW WINDOW PANES NEED TO BE REDONE, ALL OF THAT STUFF. SO SOME SOFFIT REPAIRS AND WE MIGHT RUN INTO SOME ISSUES, MAYBE WITH THE GUTTER SYSTEM WHEN WE START GETTING IN AND ACTUALLY START DOING SOME OF THOSE REPAIRS. BUT WE'RE GOING TO BE STARTING THIS NEXT WEEK. OR ARE THE CONTRACTOR SLATED TO START NEXT WEEK? WE ARE LOOKING AT PROBABLY ABOUT THREE MONTHS OR SO. NOW, THAT IS OBVIOUSLY, YOU KNOW, DEPENDENT ON WEATHER. SO IT CAN GET DELAYED. BUT AGAIN, IT SHOULDN'T CHANGE MUCH. IT'S JUST WHATEVER WOOD IS ROTTED OR THEY'RE JUST REPLACING IT AND THEN REPAINTING IT THE SAME COLOR. SO ANY QUESTIONS ON THE BROWN HOUSE.

ALL RIGHTY. SO THIS WAS A NEW ONE THAT WAS ACTUALLY ADDED. AFTER BUDGET. IT'S THE DOG PARK LIGHTING. SO I DON'T KNOW IF ANY OF YOU USE THE DOG PARK. BUT YOU KNOW, AT NIGHT, WE'VE ONLY GOT ONE LIGHT IN EACH PADDOCK. IT DOESN'T REALLY LIGHT UP THE PADDOCK A LOT. SO WE'VE HAD SOME REQUESTS TO MAYBE ADD SOME MORE PERIMETER LIGHTING OR SOMETHING TO BASICALLY LIGHT UP THESE PADDOCKS TO WHERE YOU CAN, YOU KNOW, BE THERE IN THE EVENING HOURS AND ALL. THE PARK DOES STAY OPEN PRETTY MUCH TILL MIDNIGHT. BUT IT JUST WASN'T VERY FEASIBLE FOR PEOPLE AFTER.

WELL, RIGHT NOW PRETTY MUCH AFTER 530. SO COUNCIL APPROVED US TO GO AHEAD AND ADD SOME MORE LIGHTING. WELL, WE WENT THE ROUTE OF SOLAR LIGHTS. JUST TO KIND OF MATCH WHAT WE'VE DONE AT THE SPLASH PAD AT EAST MEADOW. AND THIS PROJECT HAS ALREADY BEEN APPROVED. WE'VE ALREADY SELECTED THE CONTRACTOR AND THE POLES HAVE ALREADY BEEN ORDERED. THEY SHOULD BE GETTING DELIVERED SOMETIME IN MARCH, AND WE'RE LOOKING TO HAVE THESE INSTALLED IN MARCH. SO JUST ABOUT THE TIME TIME CHANGE COMES AROUND. WE SHOULD HAVE THE LIGHTS INSTALLED. SO BUT AT LEAST FOR NEXT FALL AND NEXT WINTER, YOU KNOW, BE ABLE TO USE IT INTO THE EVENING HOURS. ANY QUESTIONS

[00:10:03]

ABOUT THAT I BELIEVE WE'RE ADDING 12. SO. ALL RIGHTY. MOVING OVER TO PIRATE'S COVE. SO THIS WAS PLAYGROUND THAT WE RELOCATED AND BUILT IN THE LAST BUDGET. SO THIS BUDGET YEAR WE'VE WE'VE HAD A LOT OF REQUESTS TO SHADE THE PLAYGROUND. NOW TYPICALLY WE PUT, YOU KNOW, INTEGRATED SHADE LIKE LITTLE ROOFS OR SOMETHING OVER THE STRUCTURES. WITH THIS ONE, WE'RE ACTUALLY LOOKING AT SHADING THE ENTIRE PLAYGROUND. AND WE'RE NOT GOING TO JUST PUT ONE BIG SHADE OVER IT. WE'RE ACTUALLY LOOKING MORE LIKE SAILS OVER THE ENTIRE PLAYGROUND. SO THAT'S GETTING STARTED. I'M ACTUALLY MEETING WITH A CONTRACTOR TOMORROW ON SITE.

WE'RE GOING TO LOOK AT IT AND, YOU KNOW, GET HIS FEEDBACK AND THEN HOPEFULLY GET THE QUOTE RIGHT AFTER THAT AND THEN MOVE INTO GETTING THAT DESIGNED AND INSTALLED. SO LOOK FOR THAT TO BE HAPPENING. DON'T HAVE A DATE OR ANYTHING RIGHT NOW OR A TIME FRAME, ONLY BECAUSE WE'RE STILL KIND OF IN THE EARLY PROCESS OF JUST GETTING, YOU KNOW, NUMBERS BACK. SO AND SINCE WE'RE ON THE SUBJECT OF PLAYGROUNDS, THE NEXT ONE'S RIVERWAY PARK AND SAGE CREEK PLAYGROUNDS, WE'RE LOOKING TO RENOVATE BOTH OF THOSE PLAYGROUNDS THIS YEAR. YOU KNOW, TYPICALLY WE LIKE TO TRY TO RENOVATE AT LEAST TWO KIND OF SMALLER NEIGHBORHOOD PLAYGROUNDS EVERY YEAR. THESE RANGE ANYWHERE BETWEEN 60 TO $80,000 A PIECE. THIS YEAR, WE SELECTED RIVERWAY AND SAGE CREEK. THEY'VE YOU KNOW, I JUST HEARD THAT WE HAD A SWING SET GO DOWN AT SAGE CREEK. SO IT'S KIND OF TIME TO START REPLACING THIS ONE. I KNOW RIVERWAY HAS STILL HAVE DAMAGE FROM THE 2016 HAILSTORM. SO, YOU KNOW, IT'S TIME TO START REPLACING THOSE. NOW WE DID GET THESE BOTH THESE PLAYGROUNDS APPROVED AT THE DECEMBER COUNCIL MEETING. NOW ALL WE'RE DOING IS WORKING ON THE COLOR RENDERINGS.

WE JUST SUBMITTED SOMETHING TO THE VENDOR ACTUALLY TODAY. WE'RE HOPING TO MAYBE GET THOSE RENDERINGS BACK EITHER LATER THIS WEEK OR EARLY NEXT WEEK. ONCE WE GET THOSE, THEY'LL GO INTO ACTUALLY ORDERING IT, MAKING THE EQUIPMENT. TYPICALLY THAT'S ABOUT A ANYWHERE FROM 11 TO 13 WEEK TIME FRAME, AND THEN THEY'RE READY TO BE INSTALLED. SO LOOK FOR THIS PROBABLY LATE SPRING EARLY SUMMER WE CAN GET THESE INSTALLED. AND THAT IS BOTH RIVERWAY AND SAGE CREEK.

YOU CAN ACTUALLY SEE THEM FROM EACH PLAYGROUND. THEY'RE THEY'RE PRETTY MUCH RIGHT AROUND THE CORNER FROM EACH OTHER. THE LAST I HAVE A QUESTION ABOUT THE PLAYGROUNDS THERE WHEN IT CAME TO VALENTINE'S PARK. AND OF COURSE THE COVID EPIDEMIC INFLUENCED SUPPLIES, I UNDERSTAND THAT. DO YOU SEE ANYTHING AFFECTING THE TIMELINE THAT YOU JUST SHARED WITH US? NO. SO THESE ARE TIMELINES THAT I JUST RECEIVED. SO YOU'RE VERY CORRECT. WHEN WE WERE WHEN WE WERE REPLACING VALENTINE, AND I BELIEVE IT WAS VALENTINE AND MAYBE KIRBY, THE TIME FRAME ON GETTING THE EQUIPMENT WAS ALMOST A YEAR THAT'S NOW BEEN FIXED TO TYPICALLY ABOUT, YOU KNOW, ANYWHERE BETWEEN 2 TO 3 MONTHS. THEY CAN GET THE EQUIPMENT. THANK YOU. YEP. THE LAST UPDATE ON PROJECTS I HAVE ARE THE SPLASH PADS. OF COURSE. YOU KNOW, AT SOME POINT I WOULD IMAGINE THIS YEAR IN MEETINGS WE WON'T BE TALKING ABOUT THE PROGRESS OF THESE SPLASH PADS, BUT EAST MEADOW, I THINK I'VE SAID THIS LAST MEETING, IT'S PRETTY MUCH COMPLETE. THERE'S REALLY JUST SOME LANDSCAPING WORK THAT OUR STAFF, PARK STAFF ARE DOING, YOU KNOW, WITH THE WEATHER AND THE, YOU KNOW, THE SNOW THAT WE JUST HAD, IT'S KIND OF DELAYED THEM A LITTLE BIT.

BUT LOOK TO LATER THIS WEEK OR EARLY NEXT WEEK, THEY'LL BE JUMPING ON THAT AND TRYING TO FINISH OUT THAT LANDSCAPING. THAT'S PRETTY MUCH ALL THAT'S LEFT WITH EAST MEADOW, OTHER THAN THE CONTRACTOR HAS TO COME BACK IN MARCH AND INSTALL THE CHEMICALS. IT'S PRETTY MUCH JUST THE LAST THING THEY DO TO BALANCE THE BALANCE TANK. AND THEN THE SPLASH PAD IS READY TO OPERATE. SO EAST MEADOW, LIKE I SAID, IS PRETTY MUCH AS FAR AS THE SPLASH PAD ITSELF. IT'S PRETTY COMPLETE. IT'S JUST MORE OF THE ESTHETICS AROUND IT. COMMUNITY PARK, THAT ONE. WE STILL GOT SOME CONCRETE WORK GOING ON AROUND THE NEW RESTROOMS. RIGHT NOW THERE'S CONCRETE WORK. THERE'S GRADING WORK AGAIN, THE SPLASH PAD ITSELF IS PRETTY COMPLETE, OTHER THAN THEY HAVE TO COME BACK IN MARCH AND DO THE CHEMICAL BALANCING AND ALL OF THAT. THE FEATURES WILL ACTUALLY BE INSTALLED. THEY WERE ACTUALLY GOING TO BE INSTALLED THIS WEEK, BUT DUE TO THE WEATHER, THAT'S PROBABLY DELAYED THEM AT LEAST A WEEK. SO HERE IN THE NEXT WEEK

[00:15:01]

OR TWO, YOU MIGHT START SEEING THE FEATURES GET INSTALLED THERE ON THE PAD, AND THEN YOU WON'T SEE THE CONTRACTOR OUT THERE AGAIN UNTIL MARCH. NOW THERE WILL BE OTHER WORK GOING ON, LIKE THE CONCRETE AND THEN THE GRADING WORK. AND THEN OF COURSE OUR STAFF WILL COME IN.

AFTERWARDS, WE'LL DO ALL THE IRRIGATION AND THE LANDSCAPING. SO ALL OF THAT IS WHAT WE HAVE TO LOOK FORWARD TO OVER THE NEXT COUPLE OF MONTHS, HOPEFULLY BEFORE APRIL. SO ANY QUESTIONS ON THE SPLASH PADS? AND THAT'S ALL PROJECT UPDATES. VERY THOROUGH. THANK YOU BRANT. NO ONE HAS ANY QUESTIONS. I COMMEND YOU AGAIN FOR YOUR THOROUGHNESS THEN. YEAH. AND THERE'LL BE A LOT MORE COMING UP. I JUST WE'VE GOT A LOT MORE PROJECTS SLATED. IT'S JUST WE DON'T HAVE A LOT OF MOVEMENT ON THEM. SO I DIDN'T WANT TO BORE Y'ALL TOO MUCH WITH JUST THROWING OUT THE NAMES OF THE PROJECTS. WE'RE LOOKING FORWARD TO SOME NEW PROJECTS. YEP. OKAY, I THINK IT'S TIME, LADIES AND GENTLEMEN, TO MOVE ON TO PROGRAM AND EVENT UPDATES. THANK YOU. THIS IS ALSO ME. JUST A COUPLE LITTLE UPDATES HERE. SO ON DECEMBER 7TH LAST MONTH WE HAD OUR VICTORIAN CHRISTMAS MARKET. THIS WAS IN CONJUNCTION WITH THE WYLIE ARTS FESTIVAL. WE HAD 23 VENDORS THERE AND MORE THAN 1500 VISITORS TOURED THE BROWN HOUSE. SO THAT WAS REALLY NICE. VERY NEXT WEEKEND, DECEMBER 14TH, WE HAD DONUTS WITH WITH SANTA 376 ATTENDED, INCLUDING FAMILY MEMBERS. SO WE HAD A REALLY GOOD TURNOUT FOR THAT COMING UP. JANUARY 25TH WE GOT HOOPIN WITH THE BLUE AND RED. THIS IS WITH THE WYLIE POLICE AND FIRE DEPARTMENT. WE'LL HAVE FOUR DIFFERENT AGE GROUPS AND THIS IS AGES 4 TO 18, WILL BE BROKEN UP INTO FOUR DIFFERENT AGE GROUPS. THEY'LL DO SOME DRILLS AND SOME CLINICS AND STUFF LIKE THAT AND THEN DO A GAME AFTERWARDS. SO THAT'LL BE GOING ON THE 25TH OF THIS MONTH. AND THEN COMING UP, WE GOT OUR SPRING AND SUMMER CAMP REGISTRATIONS. PROGRAMING IS IN PROGRESS RIGHT NOW. AND THEN REGISTRATION WILL OPEN UP ON MARCH 1ST. SO IF YOU ARE INVOLVED IN THOSE CAMPS, YOU MIGHT WANT TO KEEP MARCH 1ST.

YOU KNOW, AND OTHER THAN THAT, THAT'S ALL THE PROGRAM UPDATES. ARE THERE ANY QUESTIONS FOR BRANT ABOUT THE PROGRAMS COMING UP CAMPS. ALL RIGHT. LAST CALL FOR QUESTIONS ABOUT CAMPS OR PROJECTS. OKAY. PROGRAMS AND EVENTS. OKAY. ALL RIGHT. WELL, IT LOOKS LIKE WE MAY HAVE COME TO THE END OF OUR FIRST MEETING OF 2025. WHAT I'D REALLY LIKE TO ASK, THOUGH, IS ANYONE OPEN TO A MOTION TO ADJOURN THIS MEETING, MISS HARRISON? I'D BE OPEN TO A MOTION TO END THIS MEETING.

YEAH, I SUPPOSE THANK YOU. I'D BE OPEN TO A SECOND TO THAT. THAT MOTION, IF WE COULD GET IT.

OH, THERE'S BRIAN, I'LL SECOND THE MOTION. ALL RIGHT. NOW WE'RE GOING TO RAISE OUR HANDS AGAIN TO VOTE. SO DON'T GO TRYING TO PUSH ANY BUTTONS. EVERYBODY WHO'S IN FAVOR OF ADJOURNING THIS MEETING, RAISE YOUR HAND. 123, FOUR. OUTSTANDING. WE'VE GOT A UNANIMOUS VOTE. AND ONCE AGAIN, THAT'S WITHOUT MISS TURNER OR MRS. SUAREZ. THANK YOU EVERYONE. VERY NICE TO SEE YOU.

HAPPY NEW YEAR AND WE'LL SEE YOU NEXT MONTH.